Warning: `cols` is now required when using `unnest()`.
ℹ Please use `cols = c(`# SECTION 1: ABOUT THE PROJECT`, `## 1a. Project
description, progress and key future events`, `## 1b. Associated projects`,
`## 1c. Procurement strategy`, `# SECTION 2: PROJECT COSTS`, `## 2a.
Performance against approved cost`, `## 2b. Reasons for variation from
approved cost`, `## 2c. Expenditure to date`, `## 2e. Unit production cost`,
`# SECTION 3: PROJECT TIMESCALE`, `## 3a. Definition of in-service date`, `##
3b. Performance against approved in-service date`, `## 3c. Reasons for
variation from approved ISD`, `## 3d. Cost resulting from ISD variation`, `#
SECTION 4: KEY USER REQUIREMENTS`, `## 4a. Performance against approved key
user requirements`, `## 4b. Reasons for variation against approved key
requirements`, `# SECTION 5: HISTORY UP TO MAIN GATE APPROVAL`, `## 5a.
Description of the Assessment Phase`, `## 5b. Cost of the Assessment Phase`,
`## 5c. Duration of Assessment Phase`, `## 5d. Cost boundaries at Initial
Gate and Main Gate Approvals`, `## 5e. ISD boundaries at Initial Gate and
Main Gate Approvals`, `## 3e. Operational impact of ISD variation`, `## 4b.
Reasons for variation against approved key user requirements`, `## 2d. Years
of peak procurement expenditure`, `## 5b. Cost of the Assessment Phase^\\^`,
`## 4a. Performance against approved key user requirements[^1]`, `## 2e. Unit
production cost[^1]`, `## 5d. Cost boundaries at Initial Gate and Main Gate
Approvals[^3]`, `# SECTION 4: KEY USER REQUIREMENTS REVISED`, `## 4b. Reasons
for variation against approved Key User Requirements`, `## 2a. Performance
against approved cost.`, `# A. The AP contracts concentrated on reducing the
risk in the proposals for the D&M phase, including demonstration of
components and subsystems to achieve an acceptable, affordable, low risk
solution. In addition, Whole Life Cost estimates were refined. Bidders’
proposals for the D&M phase were submitted on 31 March 2004.`, `## 3c.
Reasons for variation from approved In Service Date`, `## 3d. Cost resulting
from In Service Date variation`, `## 3e. Operational impact of In Service
Date variation`, `## 5e. In Service Date boundaries at Initial Gate and Main
Gate Approvals`, `## 2e. Unit production cost \\`, `## 2e. Unit production
cost∗`, `## 3b. Performance against revised ISD Revised ISD 1`, `## 3c.
Historic Performance against original ISD framework`, `## A.1. The
Requirement`, `## A.2. The Assessment Phase`, `## A.3. Progress`, `## A.4.
Capability Risks`, `## A.5. Associated Projects – not applicable`, `## A.6.
Procurement Strategy`, `## A.7. Support Strategy`, `# B. Section B: Cost`,
`## B.1. Cost of the Assessment Phase`, `## B.2. Planned/Actual Cost
Boundaries for Demonstration and Manufacture Phase/PFI`, `## B.3. Cost
Boundaries of the Demonstration and Manufacture (D&M) Phase`, `### B.3.1.
Cost Variation against approved Cost of the D&M Phase`, `### B.3.1.1. A400M`,
`### B.3.2. Operational Impact of Cost Variations of the Demonstration and
Manufacture (D&M) Phase`, `## B.4. Unit production cost`, `## B.5. Progress
against approved Support/PFI Cost - not applicable`, `# C. Section C:
Timescale`, `## C.1. Duration of the Assessment Phase`, `## C.2. Planned /
Actual Boundaries for introduction of the Capability`, `## C.3. In Service
Date`, `## C.3.1 Definition`, `## C.3.2 Progress against approved Dates`, `##
C.3.3 Timescale variation`, `### C.3.3.1 A400M`, `### C.3.4. Other costs
resulting from Timescale variation`, `### C.3.5. Operational Impact of In
Service Date variation`, `## C.4. Initial Operating Capability`, `### C.4.1.
Definition`, `### C.4.2. Progress against approved Dates – not applicable`,
`## C.4.3 Timescale variation – not applicable`, `### C.4.4. Other costs
resulting from Timescale variation – not applicable`, `### C.4.5. Operational
Impact of Initial Operating Capability variation`, `## C.5. Full Operating
Capability – not applicable`, `## C.6. Support / Service / PFI Contract – not
applicable`, `# D. Section D: Performance`, `## D.1. Readiness Levels`, `###
D.1.1. Project`, `## D.2. Performance against Lines of Development`, `###
D.2.1.1. Defence Lines of Development Variation`, `## D.3. Performance
against Key Performance Measures`, `### D.3.1. A400M`, `### D.3.1.1.
Performance against Key Performance Measures`, `### D.3.1.2. Key Performance
Measures Variation`, `### D.3.2. Support Contract – not applicable`, `## A.5.
Associated Projects`, `## B.2. Planned / Actual Cost Boundaries for
Demonstration and Manufacture Phase / PFI`, `## B.3. Cost of the
Demonstration and Manufacture (D&M) Phase`, `### B.3.1.1. Boats 1-3`, `###
B.3.1.2. Boat 4 Variation`, `### B.3.2. Operational Impact of Cost Variations
of D&M Phase`, `## B.5. Progress against approved Support / Service / PFI
Cost`, `### B.5.1. Cost Variation against approved Support / Service / PFI
Cost`, `### B.5.1.1. Initial Astute Support Solution`, `### B.5.1.2 Astute
Class Training Service Boats 1-3`, `### B.5.2. Operational Impact of Support
/ Service / PFI Cost Variations`, `### C.3.1. Definition`, `### C.3.2.
Progress against approved Dates`, `### C.3.3. Timescale variation`, `###
C.3.3.1. Boats 1-3`, `### C.3.3.2. Boat 4`, `### C.4.2. Progress against
approved Dates`, `### C.4.3. Timescale variation – not applicable`, `## C.5.
Full Operating Capability`, `### C.5.1. Definition`, `### C.5.2. Progress
Report`, `## C.6. Support / Service / PFI Contract`, `### C.6.1. Scope of
Support / Service / PFI Contract`, `### C.6.2. Progress against approved
Support / Service / PFI Contract Go-Live Date`, `### C.6.2.1. Go-Live Date
Variation`, `### C.6.2.2. Go-Live Date Variation`, `### C.6.2.3. Go-Live Date
Variation`, `### C.6.3. Progress against approved End of Support / Service /
PFI Contract Date`, `### C.6.3.1. End of Contract Date Variation`, `###
C.6.4. Operational Impact of Support / Service / PFI Support Contract
Variation`, `### D.1.1. Boats 1-3`, `### D.1.2. Boat 4`, `### D.3.1. Boats
1-3`, `### D.3.1.3. Operational Impact of variation`, `### D.3.2. Boat 4`,
`### D.3.2.1. Performance against Key Performance Measures`, `### D.3.2.2.
Key Performance Measures Variation`, `### D.3.2.3. Operational Impact of
variation`, `### D.3.3. Support Contract – not appliable`, `# A. Section A:
The Project`, `## B.2. Planned/Actual Cost Boundaries for Demonstration and
Assessment Phase/PFI`, `### B.3.1.1. Beyond Visual Range Air-to-Air Missile`,
`## B.5. Performance against approved Support/Service/PFI Cost – not
applicable`, `# C.2 Planned / Actual Boundaries for introduction of the
Capability`, `# C.3 In Service Date`, `### C.3.3.1 Beyond Visual Range
Air-to-Air Missile – variations against original In-Service Date definition`,
`## C.3.4 Other costs resulting from Timescale variation`, `## C.3.5
Operational Impact of In Service Date variation`, `# C.4 Initial Operating
Capability`, `## C.4.1 Definition`, `## C.4.2 Progress against approved
Dates`, `## C.4.4 Other costs resulting from Timescale variation – not
applicable`, `## C.4.5 Operational Impact of Initial Operating Capability
variation –`, `# C.5 Full Operating Capability`, `## C.5.1 Definition`, `#
C.6 Support / Service / PFI Contract – not applicable`, `## D.1.1 Beyond
Visual Range Air-to-Air Missile`, `## D.2. Performance against Lines of
Development[^1]`, `## D.2.1 Defence Lines of Development Variation`, `###
D.3.1. Beyond Visual Range Air-to-Air Missile`, `### B.3.1.1. Falcon
Increment A`, `### B.3.1.2. Falcon Increment C`, `## B.4. Unit production
cost – not applicable`, `## B.5. Performance against approved Support Cost`,
`### B.5.1. Cost Variation against approved Support Cost`, `### B.5.1.1.
Falcon Support Contract`, `### B.5.2. Operational Impact of Support Cost
Variations`, `## C.2. Planned/Actual Boundaries for introduction of the
Capability`, `### C.3.3.1. Falcon Increment A`, `### C.3.3.2. Falcon
Increment C`, `### C.4.3. Timescale variation not applicable`, `### C.4.4.
Other costs resulting from Timescale variation not applicable`, `### C.4.5.
Operational Impact of Initial Operating Capability variation not applicable`,
`## C.6. Support Contract`, `### C.6.1. Scope of Contract`, `### C.6.2.
Performance against approved Contract Go-Live Date`, `### C.6.2.1. Falcon
Increment A Go-Live Date Variation`, `### C.6.2.2. Falcon Increment C Go-Live
Date Variation`, `### C.6.3. Performance against approved End of Contract
Date`, `### C.6.4. Operational Impact of Support Contract variation`, `###
D.1.1. Falcon Increment A`, `### D.1.2. Falcon Increment C`, `### D.2.1.1.
Defence Lines of Development Variation:`, `### D.3.1. Falcon`, `### D.3.1.1.
Falcon Increment A`, `### D.3.1.2. Falcon Increment C`, `### D.3.1.3. Falcon
Increment A and C - Key Performance Measures Variation`, `### D.3.1.4.
Operational Impact of variation`, `## A.7. Support Strategy – not
applicable`, `## B.2. Cost Boundaries for Demonstration and Assessment
Phase/PFI`, `### B.3.1.1. System Development and Demonstration`, `###
B.3.1.2. Production Sustainment and Follow on Development`, `## B.4. Unit
production cost[^1] - not applicable`, `### C.3.3. Timescale variation - not
applicable`, `### C.3.4. Other costs resulting from Timescale variation - not
applicable`, `### C.4.2. Progress against approved Dates - not applicable`,
`### C.4.3. Timescale variation - not applicable`, `### C.4.4. Other costs
resulting from Timescale variation - not applicable`, `### C.4.5. Operational
Impact of Initial Operating Capability variation - not applicable`, `###
C.5.2. Progress Report - not applicable`, `## C.6. Support Contract – not
applicable`, `### D.3.1. Joint Combat Aircraft`, `## B.3. Cost of the
Demonstration and Manufacture (D&M) Phase – not applicable`, `## B.5.
Performance against approved Support/Service PFI Cost`, `### B.5.1. Cost
Variation against approved Support/Service PFI Cost`, `### B.5.1.1. Project
Date Variation (£m) Factor Reason for Variation`, `### B.5.2. Operational
Impact of Support/Service PFI Cost Variations`, `### C.3.3.1. Future
Strategic Tanker Aircraft`, `### C.4.3. Timescale variation`, `### C.6.1.
Scope of Contract</td>`, `### D.1.1. Future Strategic Tanker Aircraft`, `###
D.2.1. Defence Lines of Development Variation`, `### D.3.1. Future Strategic
Tanker Aircraft – not applicable`, `### D.3.2. Support Contract`, `## B.2.
Planned /Actual Cost Boundaries for Demonstration and Manufacture Phase/PFI`,
`### B.3.1.1. Lynx Wildcat Date Variation (£m) Factor Reason for Variation`,
`### B.3.1.2. Operational Impact of Cost Variations of the Demonstration and
Manufacture (D&M) Phase`, `## B.5. Progress against approved
Support/Service/PFI Cost –not applicable`, `### C.3.3.1. Project- Battlefield
Reconnaissance Helicopter`, `### C.3.3.2. Project - Surface Combatant
Maritime Rotorcraft`, `### D.3.1. Battlefield Reconnaissance Helicopters`,
`### D.3.2. Surface Combatant Maritime Rotorcraft`, `## D.4. Support Contract
– not applicable`, `## B.2. Cost Boundaries for Demonstration and Manufacture
Phase`, `### B.3.1.1. Merlin Capability Sustainment Programme Date Variation
(£m) Factor Reason for Variation`, `## B.5. Performance against approved
Support/PFI Cost – not applicable`, `## C.2. In Service Date`, `### C.2.1.
Definition`, `### C.2.2. Progress against approved Dates`, `### C.2.3.
Timescale variation`, `### C.2.3.1. Merlin Capability Sustainment Programme`,
`### C.2.4. Other costs resulting from Timescale variation`, `### C.2.5.
Operational Impact of In Service Date variation`, `### C.3.2. Progress
against approved Dates –not applicable`, `### C.3.3. Timescale variation –not
applicable`, `### C.3.4. Other costs resulting from Timescale variation –not
applicable`, `### C.3.5. Operational Impact of Initial Operating Capability
variation`, `## C.4. Full Operating Capability`, `### C.4.2. Progress
Report`, `### C.5.1. Scope of Contract`, `### C.5.2. Performance against
approved Contract Go-Live Date`, `### C.5.2.1. Go-Live Date Variation – not
applicable`, `### C.5.3. Performance against approved End of Contract Date`,
`### C.5.3.1. End of Contract Date Variation – not applicable`, `### C.5.3.2.
Operational Impact of Support Contract variation – not applicable`, `###
D.3.1. Project`, `## B.2. Planned / Actual Cost Boundaries for Demonstration
& Manufacture Phase / PFI`, `### B.3.1.1. Queen Elizabeth Class`, `## B.5.
Performance against approved Support Cost – not applicable`, `### C.3.3.1.
Queen Elizabeth Class`, `## B.1. Cost of the Assessment Phase – not
applicable`, `### B.3.1.1. Support Vehicle Variation`, `## B.5.1 Cost
Variation against approved Support / Service / PFI Cost`, `### B.5.1.1
Project`, `## C.1. Duration of the Assessment Phase</td>`, `### C.3.3.1.
Project`, `### C.4.3. Timescale Variation – not applicable`, `### C.6.1.
Scope of Support /Service / PFI Contract`, `### D.2.1.1 Defence Lines of
Development Variation`, `## D.3. Performance against Key Performance
Measures^8^`, `### D.3.1. Support Vehicle (Cargo and Recovery)`, `### D.3.1.2
Key Performance Measures Variation`, `### D.3.2. Support Vehicle (Cargo
Only)`, `### D.3.3. Support Vehicle (Recovery only)`, `### D.3.3.1.
Performance against Key Performance Measures`, `### D.3.3.2. Key Performance
Measures Variation`, `### D.3.3.3. Operational Impact of variation`, `###
D.3.4. Support Contract – not applicable`, `### B.3.1.1. Terrier`, `## B.5.
Progress against approved Support/PFI Cost`, `### B.5.1. Cost Variation
against approved Support/PFI Cost`, `### B.5.1.1. Project`, `### B.5.2.
Operational Impact of Support/PFI Cost Variations`, `### C.3.3.1. Terrier`,
`### C.5.2. Progress Report – not applicable`, `### C.6.2. Progress against
approved Contract Go-Live Date – not applicable`, `### C.6.2.1. Go-Live Date
Variation – not applicable`, `### C.6.3. Progress against approved End of
Contract Date – not applicable`, `### C.6.3.1. End of Contract Date Variation
– not applicable`, `### C.6.4. Operational Impact of Support Contract
variation – not applicable`, `## B.2. Planned / Actual Cost Boundaries for
Demonstration and Manufacture Phase/PFI`, `### B.3.1.1. Project`, `###
C.4.3.1. Project – not applicable`, `### C.5.3. Timescale variation – not
applicable`, `### C.5.4. Other costs resulting from Timescale variation – not
applicable`, `### C.5.5. Operational Impact of Full Operating Capability
variation –`, `# C.6 Support / Service / PFI Contract`, `## C.6.1 Scope of
Contract`, `## C.6.2 Progress against approved Contract Go-Live Date`, `###
C.6.2.1 Go-Live Date Variation`, `## C.6.3 Progress against approved End of
Contract Date – not applicable`, `## C.6.4 Operational Impact of Support
Contract variation – not applicable`, `# D.1 Readiness Levels`, `# D.2
Performance against Lines of Development`, `### D.3.1. Performance against
Key Performance Measures`, `## A.1. The Requirement Typhoon`, `## A.2. The
Assessment Phase Typhoon`, `## A.6. Procurement Strategy – Typhoon`, `## A.7.
Procurement Strategy – Typhoon Future Capability Programme`, `## A.8. Support
Strategy`, `### B.3.1.1. Typhoon`, `### B.3.1.2. Typhoon Future Capability
Programme`, `## B.5. Performance against approved Support/PFI Cost`, `###
C.3.3.1. Typhoon`, `### C.4.5. Operational Impact of Initial Operating
Capability variation–`, `### C.6.2. [^1]Performance against approved Contract
Go-Live Date –`, `### C.6.3. Performance against approved End of Contract
Date – not applicable`, `### D.1.1. Typhoon`, `### D.1.2. Typhoon Future
Capability Programme`, `### D.2.2. Typhoon`, `### D.2.2.1. Performance
against Key Performance Measures`, `### D.2.2.2. Key Performance Measures
Variation`, `### D.2.2.3. Operational Impact of variation`, `### D.2.3.
Typhoon Future Capability Programme`, `### D.2.3.1. Performance against Key
Performance Measures`, `### D.2.3.2. Key Performance Measures Variation`,
`### D.2.4. Support Contract`, `### D.2.4.1. Performance against Key
Performance Measures`, `### D.2.4.2. Key Performance Measures Variation`,
`### D.2.4.3. Operational Impact of variation`, `## A.3. Progress United
Kingdom Military Flying Training System`, `### B.3.1.1. United Kingdom
Military Flying Training System`, `### B.3.1.2. Increment A - Advanced Jet
Trainer`, `### B.3.1.3. Increment B – Advanced Jet Trainer Operational
Capability 2`, `### B.3.1.4. Increment C – Training System Partner`, `###
B.3.1.5. Increment D – Rear Crew Stage 1 – not applicable`, `### B.3.1.6.
Increment E – Rear Crew Stage 2 – not applicable`, `### B.3.1.7. Increment F
– Multi Engine – not applicable`, `### B.3.1.8. Increment G – Basic Trainer –
not applicable`, `### B.3.1.9. Increment H – Rotary Wing – not applicable`,
`### B.3.1.10. Increment J – Elementary Flying Training – not applicable`,
`## B.5. Performance against approved Support/Service/ PFI Cost`, `### B.5.1.
Cost Variation against approved Support/Service/ PFI Cost`, `### B.5.1.1.
United Kingdom Military Flying Training System`, `### B.5.1.2. Increment A –
Advanced Jet Trainer (Interim Support)`, `### B.5.1.3 Increment B – Advanced
Jet Trainer Operational Capability 2`, `### B.5.1.4 Increment C – United
Kingdom Military Flying Training System (Training System Partner and
Headquarters)`, `### B.5.1.5 Increment D – Rear Crew Stage 1 – not
applicable`, `### B.5.1.6 Increment E – Rear Crew Stage 2 – not applicable`,
`### B.5.1.7 Increment F – Multi Engine – not applicable`, `### B.5.1.8
Increment G – Basic Trainer – not applicable`, `### B.5.1.9 Increment H –
Rotary Wing – not applicable`, `### B.5.1.10 Increment J – Elementary Flying
Training – not applicable`, `### B.5.2. Operational Impact of
Support/Service/PFI Cost Variations – not applicable`, `### C.3.3.1. United
Kingdom Military Flying Training System`, `### C.3.3.2. Increment A -
Advanced Jet Trainer`, `### C.3.3.3. Increment B – Advanced Jet Trainer
Operational Capacity 2`, `### C.3.3.4. Increment C Ready for Training Uses
Date 1– United Kingdom Military Flying Training System (Advanced Jet Trainer
Ground based training Environment)`, `### C.3.3.5. Increment C Ready for
Training Uses Date 2– United Kingdom Military Flying Training System
(Advanced Jet Trainer Ground based training Environment)`, `### C.3.3.6.
Increment D – Rear Crew Stage 1 – not applicable`, `### C.3.3.7. Increment E
– Rear Crew Stage 2 – not applicable`, `### C.3.3.8. Increment F – Multi
Engine – not applicable`, `### C.3.3.9. Increment G – Basic Trainer – not
applicable`, `### C.3.3.10. Increment H – Rotary Wing – not applicable`, `###
C.3.3.11. Increment J – Elementary Flying Training – not applicable`, `##
C.6. Support/Service/PFI Contract`, `### C.6.1. Scope of Support/Service/PFI
Contract`, `### C.6.2. Performance against approved Support/Service/PFI
Contract Go-Live Date`, `### C.6.3. Performance against approved End of
Support/Service/PFI Contract Date`, `### C.6.4. Operational Impact of
Support/Service/PFI Support Contract variation – not applicable`, `### D.1.1.
United Kingdom Military Flying Training System`, `### D.1.2. Increment A –
Advanced Jet Trainer`, `### D.1.3. Increment B – Advanced Jet trainer
Operational Capability 2`, `### D.1.4. Increment C Training System Partner`,
`### D.1.5. Increment D – Rear Crew Stage 1 – not applicable`, `### D.1.6.
Increment E – Rear Crew Stage 2 – not applicable`, `### D.1.7. Increment F –
Multi Engine – not applicable`, `### D.1.8. Increment G – Basic Trainer – not
applicable`, `### D.1.9. Increment H – Rotary Wing – not applicable`, `###
D.1.10. Increment J – Elementary Flying Training – not applicable`, `###
D.3.1. United Kingdom Military Flying Training System`, `### D.3.2. Increment
A - Advanced Jet Trainer`, `### D.3.3. Increment B – Advanced Jet Trainer
Operational Capability 2`, `### D.3.4. Increment C – Training System
Partner`, `### D.3.4.1. Performance against Key Performance Measures`, `###
D.3.4.2. Key Performance Measures Variation`, `### D.3.5. Increment D – Rear
Crew Stage 1 – not applicable`, `### D.3.6. Increment E – Rear Crew Stage 2 –
not applicable`, `### D.3.7. Increment F – Multi engine – not applicable`,
`### D.3.8. Increment G – Basic Trainer – not applicable`, `### D.3.9.
Increment H – Rotary Wing – not applicable`, `### D.3.10. Increment J –
Elementary Flying Training – not applicable`, `## A.4. Capability Risks.`,
`### B.3.1.1. Watchkeeper`, `## B.5. Progress against approved Support/PFI
Cost – not applicable`, `### C.3.3.1. Watchkeeper`, `### A.7.1. Support /
Service / PFI Contract Strategy`, `### B.5.2. Operational Impact of Support /
Service / PFI Cost Variations –`, `## B.6. Expenditure to date`, `## C.3.
Initial Operating Capability/In Service Date`, `### C.3.1. Definition of
Initial Operating Capability/In Service Date`, `### C.3.4. Other costs
resulting from Timescale variation – not applicable`, `### C.3.5. Operational
Impact of In-Service Date/Initial Operating Capability variation – not
applicable`, `## C.5. Support / Service / PFI Contract`, `### C.5.1. Scope of
Support / Service / PFI Contract`, `### C.5.2. Progress against approved
Support / Service / PFI Contract Go-Live Date`, `### C.5.3. Progress against
approved End of Support / Service / PFI Contract Date`, `### C.5.4.
Operational Impact of Support / Service / PFI Support Contract variation –
not applicable`, `## D.1. Maturity Measures`, `## D.2. Performance against
Defence Lines of Development`, `### D.3.2.2. Key Performance Measures
Variation – not applicable`, `### D.3.2.3. Operational Impact of variation–
not applicable`, `## A.7. Support Strategy – Not Applicable`, `## B.3. Cost
of the Demonstration and Manufacture Phase`, `### B.3.1. Cost Variation
against approved Cost of the Demonstration &`, `### B.3.1.1. System
Development & Demonstration`, `### B.3.1.2. Production, Sustainment &
Follow-on-Development Date Variation (£m) Factor Reason for Variation`, `###
B.3.2. Operational Impact of Cost Variations of Demonstration & Manufacture
Phase`, `## B.5. Progress against approved Support / Service / PFI Cost – not
applicable`, `## C.2. Planned / Actual Boundaries for introduction of the
Capability –`, `## C.3. In-Service Date/Initial Operating Capability`, `###
C.3.2. Progress against approved Dates – not applicable`, `### C.3.3.
Timescale variation – not applicable`, `### C.4.2. Progress Report – not
applicable`, `## C.5. Support / Service / PFI Contract – not applicable`,
`### D.1.1. Joint Combat Aircraft`, `### D.2.2. Joint Combat Aircraft`, `###
D.2.3. Support Contract – not applicable`, `## A.5. Associated Projects – Not
Applicable`, `### B.3.1.1. Lynx Wildcat`, `## B.5. Progress against approved
Support / Service / PFI Cost – Not Applicable`, `### C.3.3.1. Battlefield
Reconnaissance Helicopter`, `### C.3.3.2. Surface Combatant Maritime
Rotorcraft`, `### C.3.4. Other costs resulting from Timescale variation – Not
Applicable`, `### C.3.5. Operational Impact of In-Service Date/Initial
Operating Capability variation – Not Applicable`, `## C.5. Support / Service
/ PFI Contract – Not Applicable`, `### D.1.1. Lynx Wildcat`, `### D.1.2.
Increment A`, `### D.3.3. Support Contract – Not Applicable`, `### B.3.1.1.
Merlin CSPt Date Variation (£m) Factor Reason for Variation`, `### C.3.3.1.
MERLIN CSP`, `# C.5 Support / Service / PFI Contract – not applicable`, `###
D.1.1. Merlin CSP`, `### D.3.1. Merlin CSP`, `### D.3.1.2. Key Performance
Measures Variation – not applicable`, `### D.3.1.3. Operational Impact of
variation- not applicable`, `## A.5. Associated Projects – not applicable.`,
`### B.3.1. Cost Variation against approved Cost of the Demonstration and
Manufacture Phase`, `### B.3.1.1. Nimrod Maritime Reconnaissance and Attack
Mk4`, `### B.3.2. Operational Impact of Cost Variations of Demonstration and
Manufacture Phase – not applicable.`, `## B.5. Progress against approved
Support / Service / PFI Cost – not applicable.`, `## C.3. In Service Date
/Initial Operating Capability`, `### C.3.3.1. Nimrod Maritime Reconnaissance
and Attack Mk4`, `### C.3.5. Operational Impact of ISD /Initial Operating
Capability variation`, `### C.4.2. Progress Report – not applicable.`, `##
C.5. Support / Service / PFI Contract - not applicable.`, `# D.`, `## D.3.3
Support Contract – not applicable`, `### B.3.2. Operational Impact of Cost
Variations of D&M Phase – Not Applicable`, `# C.1 Duration of the Assessment
Phase`, `# C.3 In-Service Date/Initial Operating Capability`, `### C.3.1.2.
Progress against approved Dates`, `## C.3.2 Timescale variation`, `###
C.3.2.1. Project`, `### C.3.3. Other costs resulting from Timescale
variation`, `### C.3.4. Operational Impact of In-Service Date`, `### C.4.2.
Progress Report – Not Applicable`, `## C.5. Support / Service / PFI Contract
– Not Applicable `, `## D.1.1 Maturity Measures`, `## D.1.1 Project`, `###
D.1.2. Increment A – Not Applicable`, `### D.3.1.2 Key Performance Measures
Variation – Not Applicable`, `### D.3.1.3. Operational Impact of variation –
Not Applicable`, `## A.5. Associated Projects – Not applicable`, `###
B.3.1.1. Project Date Variation (£m) Factor Reason for Variation`, `###
B.5.1.1. Tornado CUS(P) Date Variation (£m) Factor Reason for Variation`,
`### C.3.3.1. Tornado CUS(P)`, `### C.3.4. Other costs resulting from
Timescale variation – Not applicable`, `### C.3.5. Operational Impact of
In-Service Date/Initial Operating Capability variation – Not applicable`,
`### C.4.2. Progress Report – Not applicable`, `### C.5.2. Progress against
approved Support / Service / PFI Contract Go-Live Date – Not applicable`,
`### C.5.3. Go-Live Date Variation – Not applicable`, `### C.5.4. Progress
against approved End of Support / Service / PFI Contract Date – Not
applicable`, `### C.5.5. Operational Impact of Support / Service / PFI
Support Contract variation – Not applicable`, `### D.1.1. Tornado CUS(P)`,
`### D.2.1.1. Defence Lines of Development Variation - Not applicable`, `###
D.3.1. Tornado CUS(P)`, `### D.3.2. Support Contract – Not applicable`, `##
B.3. Cost of the Demonstration & Manufacture Phase`, `### B.3.1.1. Type 45
Destroyer`, `### B.5.1.1. Type 45 Destroyer Date Variation (£m) Factor Reason
for Variation`, `### C.3.3.1. Type 45 Destroyer`, `### C.3.5. Operational
Impact of In-Service Date/Initial Operating Capability variation`, `###
C.5.2.1. Go-Live Date Variation`, `### C.5.3.1. End of Contract Date
Variation – Not applicable`, `### C.5.4. Operational Impact of Support /
Service / PFI Support Contract variation`, `### D.1.1. Type 45 Destroyer`,
`### D.3.1. Type 45 Destroyer`, `### D.3.2.2. Key Performance Measures
Variation – Not applicable`, `### D.3.2.3. Operational Impact of variation –
Not applicable`, `### B.3.1.2. Typhoon Future Capability Programme Date
Variation (£m) Factor Reason for Variation`, `### B.5.1. Cost Variation
against approved Support / Service / PFI Cost –`, `### B.5.2. Cost Variation
against approved Increment A – not applicable`, `### B.5.3. Operational
Impact of Support / Service / PFI Cost Variations –`, `### C.5.2. Progress
against approved Contract Go-Live Date – not applicable`, `### C.5.3.
Progress against approved Contract Date – not applicable`, `### C.5.4.
Operational Impact of Contract variation – not applicable`, `### D.3.1.
Typhoon`, `### D.3.1.3. Operational Impact of variation – not applicable`,
`### D.3.2. Typhoon Future Capability Programme`, `### D.3.3. Support
Contract`, `### D.3.3.2. Key Performance Measures Variation – not
applicable`, `### D.3.3.3. Operational Impact of variation – not applicable`,
`### B.3.1.1. United Kingdom Military Flying Training System – not
applicable`, `### B.3.1.4. Increment C – Training System Partner – not
applicable`, `### B.3.1.5. Increment D – Rear Crew Stage 1`, `### B.3.2.
Operational Impact of Cost Variations of the Demonstration and Manufacture
Phase – not applicable`, `## B.5. Progress against approved Support/Service/
PFI Cost`, `### B.5.1.1. United Kingdom Military Flying Training System – not
applicable`, `### B.5.1.2 Increment A – Advanced Jet Trainer`, `### B.5.1.5
Increment D – Rear Crew Stage 1 –not applicable`, `### B.5.2. Operational
Impact of Support/Service/PFI Cost Variations –`, `## C.3. In Service
Date/Initial Operating Capability`, `### C.3.3.1. United Kingdom Military
Flying Training System – not applicable.`, `### C.3.3.3. Increment B –
Advanced Jet Trainer Operational Capacity 2 –`, `### C.3.3.6. Increment D –
Rear Crew Stage 1`, `### C.3.5. Operational Impact of In Service Date/Initial
Operating Capability variation`, `## C.5. Support/Service/PFI Contract`, `###
C.5.1. Scope of Support/Service/PFI Contract`, `### C.5.2. Progress against
approved Support/Service/PFI Contract Go-Live Date`, `### C.5.2.1. Increment
C Go-Live Date Variation`, `### C.5.3. Progress against approved End of
Support/Service/PFI Contract Date`, `### C.5.3.1. End of Contract Date
Variation`, `### C.5.4. Operational Impact of Support/Service/PFI Support
Contract variation – not applicable`, `# D.1 Maturity Measures`, `## D.1.1
United Kingdom Military Flying Training System – not applicable`, `## D.1.2
Increment A – Advanced Jet Trainer`, `## D.1.3 Increment B – Advanced Jet
Trainer Operational Capability 2`, `## D.1.4 Increment C – Training System
Partner – not applicable`, `## D.1.5 Increment D – Rear Crew Stage 1`, `##
D.1.6 Increment E – Rear Crew Stage 2 – not applicable`, `## D.1.7 Increment
F – Multi Engine – not applicable`, `## D.1.8 Increment G – Basic Trainer –
not applicable`, `## D.1.9 Increment H – Rotary Wing – not applicable`, `##
D.1.10 Increment J – Elementary Flying Training – not applicable`, `###
D.3.2.2 Key Performance Measures Variation`, `### D.3.2.3. Operational Impact
of variation – not applicable`, `## D.3.3 Increment B – Advanced jet trainer
Operational capability 2`, `### D.3.3.1 Performance against Key Performance
Measures`, `### D.3.3.2 Key Performance Measures Variation`, `### D.3.3.3
Operational Impact of variation – not applicable`, `## D.3.4 Increment C –
Training System Partner – not applicable`, `## D.3.5 Increment D – Rear Crew
Stage 1`, `### D.3.5.1 Performance against Key Performance Measures`, `##
D.3.6 Increment E – Rear Crew Stage 2 – not applicable`, `## D.3.7 Increment
F – Multi engine – not applicable`, `## D.3.8 Increment G – Basic Trainer –
not applicable`, `## D.3.9 Increment H – Rotary Wing – not applicable`, `##
D.3.10 Increment J – Elementary Flying Training – not applicable`, `###
C.3.5. Operational Impact of In-Service Date/Initial Operating Capability
variation – not Applicable`, `### D.1.1. Watchkeeper`, `### D.3.1.
Watchkeeper`, `### A.7.1. Support Strategy`, `### B.3.2. Operational Impact
of Cost Variations of Demonstration and Manufacture Phase`, `## B.5. Progress
against approved Support / Service / PFI Cost – Not applicable`, `## C.3.
In-Service Date`, `### C.3.3.1. A400M`, `## C.4. Full Operating Capability –
Not applicable`, `## C.5. Support / Service / PFI Contract – Not applicable`,
`### D.1.1. A400M`, `### D.3.1.2. Key Performance Measures Variation – Not
applicble`, `### D.3.1.3. Operational Impact of variation – Not applicble`,
`### A.7.1. Support / Service / Private Finance Initiative Contract
Strategy`, `## B.2. Planned / Actual Cost Boundaries for Demonstration and
Manufacture Phase / Private Finance Initiative`, `### B.3.1.2. Boat 4`, `###
B.3.1.3. Boat 5`, `### B.3.1.4. Boat 6`, `### B.3.2. Operational Impact of
Cost Variations of Demonstration & Manufacturing Phase`, `## B.5. Progress
against approved Support / Service / Private Finance Initiative Cost`, `###
B.5.1. Cost Variation against approved Support / Service / Private Finance
Initiative Cost`, `### B.5.1.1. Initial Astute Support Solution Date
Variation (£m) Factor Reason for Variation`, `### B.5.2. Cost Variation
against approved Increment A`, `### B.5.2.1. Astute Class Training Service
Boats 1-3`, `### B.5.2.2 Astute Class Training Service Boat 4`, `### B.5.3.
Operational Impact of Support / Service / Private Finance Initiative Cost
Variations`, `### C.3.3.3. Boat 5`, `### C.3.3.4. Boat 6`, `## C.5. Support /
Service / Private Finance Initiative Contract`, `### C.5.1. Scope of Support
/ Service / Private Finance Initiative Contract`, `### C.5.2. Progress
against approved Support / Service / Private Finance Initiative Contract
GoLive Date`, `### C.5.2.1. Go-Live Date Variation – Initial Astute Support
Solution`, `### C.5.2.2. Go-Live Date Variation – Astute Class Training
Service Boats 1-3`, `### C.5.2.3. Go-Live Date Variation – Astute Class
Training Service Boats 1-4`, `### C.5.3. Progress against approved End of
Support / Service / Private Finance Initiative Contract Date`, `### C.5.4.
Operational Impact of Support / Service / Private Finance Initiative Support
Contract variation`, `### D.3.1.2. Key Performance Measures Variation – Not
applicable`, `### D.3.1.3. Operational Impact of variation – Not applicable`,
`### D.3.3. Support Contract – Not applicable`, `### C.3.3.1. Beyond Visual
Range Air-to-Air Missile -– variations against original In-Service Date
definition`, `### D.1.1. Beyond Visual Range Air-to-Air Missile`, `###
D.2.1.1. Defence Lines of Development Variation – not applicable`, `###
D.3.3. Support Contract – not applicable`, `## A.7.1 Support / Service / PFI
Contract Strategy`, `### B.3.1.1. Increment A`, `### B.3.1.2. Increment C`,
`## B.4. Unit production cost N/A`, `### B.5.1. Cost Variation against
approved Cost`, `### B.5.2. Cost Variation against approved Increment A – Not
Applicable`, `### B.5.2.1. Project – Not Applicable`, `### C.5.2. Progress
against approved Support Contract Go-Live Date`, `### C.5.2.2.1. Increment
A`, `### C.5.2.2 2. Increment C`, `### C.5.3. Progress against approved End
of Support Contract Date`, `### C.5.3.1. End of Contract Date Variation – Not
Applicable`, `### C.5.4. Operational Impact of Support / Service / PFI
Support Contract variation – Not Applicable`, `### D.1.1. Increment A`, `###
D.1.2. Increment C`, `### D.2.1.2 Increment C`, `### D.3.1. Increment A`,
`### D.3.1.2 Increment C`, `### D.3.1.2. Key Performance Measures Variation
Increments A and C`, `### D.3.2. Support Contract – Not Applicable`, `# A.1
The Requirement`, `# A.2 The Assessment Phase`, `# A.3 Progress`, `# A.4
Capability Risks`, `# A.5 Associated Projects`, `# A.6 Procurement Strategy`,
`# A.7 Support Strategy`, `# B.1 Cost of the Assessment Phase`, `# B.2
Planned / Actual Cost Boundaries for Demonstration and Manufacture Phase /
PFI`, `# B.3 Cost of the Demonstration and Manufacture Phase`, `## B.3.1 Cost
Variation against approved Cost of the Demonstration &`, `### B.3.1.1 Lynx
Wildcat`, `## B.3.2 Operational Impact of Cost Variations of Demonstration &
Manufacture Phase`, `# B.4 Unit production cost/Quantities required`, `# B.5
Progress against approved Support / Service / PFI Cost`, `# B.6 Expenditure
to date`, `# C.2 Planned / Actual Boundaries for In-Service Date or Initial
Operating Capability`, `### C.3.3.1 Battlefield Reconnaissance Helicopter`,
`### C.3.3.2 Surface Combatant Maritime Rotorcraft`, `## C.3.4 Other costs /
savings resulting from Timescale variation`, `## C.3.5 Operational Impact of
In-Service Date/Initial Operating Capability variation`, `## D.2.1
Performance against Defence Lines of Development`, `## D.2.2 Defence Line of
Development Variation`, `## D.3.1 Battlefield Reconnaissance Helicopters`,
`### D.3.1.1 Performance against Key Performance Measures`, `### D.3.1.3
Operational Impact of variation`, `## D.3.2 Surface Combatant Maritime
Rotorcraft`, `### D.3.2.1 Performance against Key Performance Measures`, `###
D.3.2.3 Operational Impact of variation`, `# D.4 Support Contract`, `###
B.3.1.1 Puma Life Extension Programme`, `## B.3.2 Operational Impact of Cost
Variations of Demonstration &`, `# C.2 Planned / Actual Boundaries for In
Service Date or Initial Operating Capability`, `## C.5.1 Scope of Support /
Service / PFI Contract`, `## C.5.2 Progress against approved Support /
Service / PFI Contract Go-Live Date`, `## C.5.3 Progress against approved
Support / Service / PFI Contract Date`, `## C.5.4 Other costs / savings
resulting from Support Cost variation`, `## C.5.5 Operational Impact of
Support / Service / PFI Support Contract variation`, `## D.3.1 Puma Life
Extension Programme`, `### B.3.1.1 Queen Elizabeth Class`, `### C.3.3.1 Queen
Elizabeth Class`, `## D.3.1 Queen Elizabeth Class`, `### B.3.1.1 Type 45
Destroyer`, `### B.5.1.1 Type 45 Destroyer Full Support`, `## B.5.2
Operational Impact on Support / Service / PFI Cost`, `### C.3.3.1 Type 45
Destroyer`, `### C.5.2.1 Go-Live Date Variation`, `### C.5.3.1 End of
Contract Date Variation`, `# C.3.2.`, `## D.3.1 Type 45 Destroyer`, `## D.4.1
Type 45 Destroyer`, `### D.4.1.1 Performance against Key Performance
Measures`, `### D.4.1.2 Key Performance Measures Variation`, `### D.4.1.3
Operational Impact of variation`, `### B.3.1.1 Typhoon`, `### B.3.1.2 Typhoon
Future Capability Programme`, `### C.3.3.1 Typhoon`, `### C.3.3.2 Typhoon
Future Capability Programme`, `## C.5.5 Operational Impact of Support /
Service / PFI Support Contract variation `, `## D.3.1 Typhoon`, `## D.3.2
Typhoon Future Capability Programme`, `## D.4.1 Typhoon`, `# A.5 Associated
Projects A.6 Procurement Strategy`, `### B.3.1.1 United Kingdom Military
Flying Training System`, `### B.3.1.1 Advanced Jet Trainer`, `### B.3.1.2
Advanced Jet Trainer Operational Capability 2`, `### B.3.1.3 Rear Crew Stage
1`, `### B.3.1.4 Rear Crew Stage 2`, `### B.5.1.1 Advanced Jet Trainer
(Support)`, `### B.5.1.2 Training System Partner and Headquarters`, `###
B.5.1.3 Advanced Jet Trainer Ground Based Training Environment`, `### B.5.1.4
Multi Engine`, `### B.5.1.5 Basic Trainer`, `### B.5.1.6 Rotary Wing`, `###
B.5.1.7 Elementary Flying Training`, `### C.3.3.1 United Kingdom Military
Flying Training System`, `### C.3.3.2 Advanced Jet Trainer`, `### C.3.3.3
Advanced Jet Trainer Operational Capability 2`, `### C.3.3.4 Rear Crew Stage
1`, `### C.3.3.5 Rear Crew Stage 2`, `### C.5.2.2 Advanced Jet Trainer
(Support)`, `### C.5.2.3 Training System Partner and Headquarters`, `###
C.5.2.4 Ready for Training Uses Date 1 - Advanced Jet Trainer Ground Based
Training Environment`, `### C.5.2.5 Ready for Training Uses Date 2 - Advanced
Jet Trainer Ground Based Training Environment`, `### C.5.2.6 Multi Engine`,
`### C.5.2.7 Basic Trainer`, `### C.5.2.8 Rotary Wing`, `### C.5.2.9
Elementary Flying Training`, `## C.5.3 Progress against approved Support /
Service / PFI Contract End Date`, `### C.5.3.2 Advanced Jet Trainer`, `###
C.5.3.3 Training System Partner and Headquarters`, `### C.5.3.4 Advanced Jet
Trainer Ground Based Training Environment`, `### C.5.3.5 Multi Engine`, `###
C.5.3.6 Basic Trainer`, `### C.5.3.7 Rotary Wing`, `### C.5.3.8 Elementary
Flying Training`, `## D.3.1 United Kingdom Military Flying Training System`,
`## D.3.2 Advanced Jet Trainer`, `## D.3.3 Advanced Jet Trainer Operational
Capability 2`, `### D.3.3.3 Operational Impact of variation`, `## D.3.4
Training System Partner and Headquarters`, `## D.3.5 Advanced Jet Trainer
Ground Based Training Environment`, `## D.3.6 Rear Crew Stage 1`, `###
D.3.6.1 Performance against Key Performance Measures`, `### D.3.6.2 Key
Performance Measures Variation`, `### D.3.6.3 Operational Impact of
variation`, `## D.3.7 Rear Crew Stage 2`, `## D.3.8 Multi Engine D.3.9 Basic
Trainer`, `## D.3.10 Rotary Wing`, `## D.3.11 Elementary Flying Training`,
`## B.3.1 Cost Variation against approved Cost of the Demonstration &
Manufacture Phase B.3.1.1 A400M`, `## D.3.1 A400M`, `### B.3.1.1
Watchkeeper`, `## B.5.1 Cost Variation against approved Support / Service /
PFI Cost B.5.1.1 Watchkeeper`, `### C.3.3.1 Watchkeeper`, `## D.3.1
Watchkeeper`, `### B.3.1.1 Astute Boats 1-3`, `### B.3.1.2 Astute Boat 4`,
`### B.3.1.3 Astute Boat 5`, `### B.3.1.4 Astute Boat 6`, `### B.5.1.1
Initial Astute Support Solution`, `### B.5.1.3 Astute Class Training Service
Boats 4`, `### C.3.3.1 Astute Boats 1-3`, `### C.3.3.2 Astute Boat 4`, `###
C.3.3.3 Astute Boat 5`, `### C.3.3.4 Astute Boat 6`, `### C.5.2.2 Astute
Class Training Service Boats 1-3`, `### C.5.2.3 Astute Class Training Service
Boats 4`, `## D.3.1 Astute Boats 1-3`, `## D.3.2 Astute Boat 4`, `### B.3.1.1
Beyond Visual Range Air-to-Air Missile`, `### C.3.3.1 Beyond Visual Range
Air-to-Air Missile - Original In Service Date`, `### C.3.3.2 Beyond Visual
Range Air-to-Air Missile - In Service Date 1`, `### C.3.3.3 Beyond Visual
Range Air-to-Air Missile - In Service Date 2`, `## D.3.1 Beyond Visual Range
Air-to-Air Missile`, `# B.3 Cost of the Demonstration and Manufacture Phase -
not applicable`, `### B.5.1.1 Future Strategic Tanker Aircraft`, `### C.3.3.1
Future Strategic Tanker Aircraft`, `## D.4.1 Future Strategic Tanker
Aircraft`, `# A.3 Project History since Main Gate`, `# A.4 In-year Progress`,
`# A.5 Capability Risks`, `# A.6 Associated Projects`, `# A.7 Procurement
Strategy`, `# A.8 Support Strategy`, `# B.2 Actual cost boundaries for
Demonstration and Manufacture Phase / PFI`, `## B.3.1 Cost variation against
approved cost of the Demonstration and Manufacture Phase`, `### B.3.1.1
Interim Main Gate 1`, `### B.3.1.2 Interim Main Gate 2- Future Local Area Air
Defence System`, `## B.3.2 Operational Impact of cost variations of
Demonstration and Manufacture Phase B.5 Expenditure to date`, `# C.1 Length
of the Assessment Phase`, `# C.2 Actual Boundaries for In Service Date or
Initial Operating Capability`, `### C.3.3.1 Loitering Munitions`, `###
C.3.3.2 Spear Capability 2 Block 1`, `### C.3.3.3 Interim Main Gate 2- Future
Local Area Air Defence System`, `## C.3.4 Other costs / savings resulting
from timescale variation`, `# D.1 Sentinel Score`, `# D.2 Performance against
Defence Lines of Development`, `## D.2.1 Loitering Munitions`, `### D.2.1.1
Performance against Defence Lines of Development`, `### D.2.1.1 Defence Line
of Development variation`, `## D.2.2 Spear Capability 2 Block 1`, `###
D.2.2.1 Performance against Defence Lines of Development`, `### D.2.2.2
Defence Line of Development variation`, `## D.2.3 Spear Capability 2 Block
2`, `## D.2.4 Interim Main Gate 2 - Future Local Area Air Defence System
Demonstration & Manufacture`, `### D.2.4.1 Performance against Defence Lines
of Development`, `### D.2.4.2 Defence Line of Development variation`, `# D.3
Key Performance Measures`, `## D.3.1 Loitering Munitions`, `### D.3.1.2 Key
Performance Measures variation`, `### D.2.3.3 Operational Impact of
variation`, `## D.3.2 Spear Capability 2 Block 1`, `### D.3.3.2 Key
Performance Measures variation`, `## D.3.3 Spear Capability 2 Block 2-
cancelled`, `## D.3.4 Interim Main Gate 2 - Future Local Area Air Defence
System D&M`, `### D.3.4.1 Performance against Key Performance Measures`, `###
D.3.4.2 Key Performance Measures variation`, `# B.2 Actual cost boundaries
for Demonstration and Manufacture Phase /`, `### B.3.1.1 Increment A`, `###
B.3.1.2 Increment C`, `### B.3.1.3 Urgent Operational Requirement`, `## B.3.2
Operational Impact of cost variations of Demonstration and Manufacture
Phase`, `# B.4 Progress against approved Support / PFI Cost`, `## B.4.1 Cost
variation against approved Support / PFI Cost`, `### B.4.1.1 Increment A`,
`### B.4.1.2 Increment C`, `### B.4.1.3 Urgent Operational Requirement`, `##
B.4.2 Operational Impact on Support / PFI Cost`, `# B.5 Expenditure to date`,
`### C.3.3.1 Increment A`, `### C.3.3.2 Increment C`, `### C.3.3.3 Urgent
Operational Requirement`, `## C.5. Support / PFI Contract`, `## C.5.1 Scope
of Support / PFI Contract`, `## C.5.2 Progress against approved Support / PFI
Contract Go-Live Date`, `### C.5.2.2 Increment C`, `### C.5.2.3 Urgent
Operational Requirement`, `## C.5.3 Progress against approved Support / PFI
Contract End Date`, `### C.5.3.2 Increment C`, `### C.5.3.3 Urgent
Operational Requirement`, `## C.5.5 Operational Impact of Support / PFI
Support Contract variation`, `## D.1. Sentinel Score`, `# D.2 Performance
against Defence Lines of Development D.2.1 Falcon Increment A`, `### D.2.1.2
Defence Line of Development variation`, `## D.2.2 Falcon Increment C`, `##
D.2.3 Urgent Operational Requirement`, `### D.2.3.1 Performance against
Defence Lines of Development`, `### D.2.3.2 Defence Line of Development
variation`, `## D.3.1 Falcon Increment A`, `## D.3.2 Falcon Increment C`,
`### D.3.2.2 Key Performance Measures variation`, `## D.3.3 Urgent
Operational Requirement`, `## D.4.1 Falcon Increment A`, `### D.4.1.2 Key
Performance Measures variation`, `# B.3 Cost of the Demonstration and
Manufacture Phase- N/A`, `### B.4.1.1 Future Strategic Tanker Aircraft`, `###
C.5.2.1 Go-Live Date Variation- N/A`, `## C.5.5 Operational Impact of Support
/ PFI Support Contract variation FUTURE STRATEGIC TANKER AIRCRAFT`, `## D.2.2
Defence Line of Development variation`, `## D.3.1 Future Strategic Tanker
Aircraft`, `# D.4 Support Contract- N/A`, `# A.3 Project History`, `###
B.3.1.1 A400M`, `### B.3.1.1 System Development & Demonstration`, `###
B.3.1.2 Production, Sustainment & Follow on Development`, `# B.4 Progress
against approved Support / PFI Cost- N/A`, `# C.2 Actual Boundaries for In
Service Date or Initial Operating Capability^3^`, `## C.3.2 Progress against
approved Dates- N/A`, `## C.3.3 Timescale variation - N/A`, `## C.5. Support
/ PFI Contract- N/A`, `## D.3.1 Joint Combat Aircraft`, `## B.3.1 Cost
variation against approved cost of the Demonstration and Manufacture Phase
B.3.1.1 Lynx Wildcat`, `### B.4.1.1 Lynx Wildcat`, `### C.3.3.1 Lynx Wildcat
- Battlefield Reconnaissance Helicopter`, `# C.3.5.`, `## D.2.1 Battlefield
Reconnaissance Helicopters`, `### D.3.1.2 comments. This refers to the
de-scope of Bowman data communications.</td>`, `## D.2.2 Surface Combatant
Maritime Rotorcraft`, `### D.3.1.2 comments. This refers to the de-scope of
Bowman data communications. Lack of clarity over uniformed support</td>`, `##
D.3.1 Lynx Wildcat - Battlefield Reconnaissance Helicoper`, `## D.3.2 Lynx
Wildcat - Surface Combatant Maritime Rotorcraft`, `### B.3.1.1 Merlin
Capability Sustainment Programme`, `### B.4.1.1 Integrated Merlin Operational
Support`, `### C.3.3.1 Merlin Capability Sustainment Programme`, `## C.3.4
Other costs / savings resulting from timescale variation C.3.5 Operational
Impact of In-Service Date/Initial Operating Capability variation`, `## D.3.1
Merlin Capability Sustainment Programme`, `## D.4.1 Integrated Merlin
Operational Support`, `### B.3.1.1 Queen Elizabeth Class Aircraft Carriers`,
`# B.4 Progress against approved Support / PFI Cost B.5 Expenditure to date`,
`### C.3.3.1 Queen Elizabeth Class Aircraft Carriers`, `### C.3.3.2
Conversion`, `## D.3.1 Queen Elizabeth Class Aircraft Carriers D.3.1.1
Performance against Key Performance Measures`, `## C.3.4 Other costs /
savings resulting from timescale variation- N/A`, `## C.3.5 Operational
Impact of In-Service Date/Initial Operating Capability variation- N/A`, `##
C.4. Full Operating Capability- N/A`, `## D.3.1 Specialist Vehicles`, `###
B.4.1.1 Type 45 Destroyer Full Support`, `# A.3 Project History Since Main
Gate`, `### B.4.1.1 Battle Group Thermal Imaging`, `### B.4.1.2 Diesel
Engines and Transmissions`, `## C.5.5 Operational Impact of Support / PFI
Support Contract variation WARRIOR CAPABILITY SUSTAINMENT PROGRAMME`, `##
D.3.1 Warrior Capability Sustainment Programme`, `### B.3.1.1 Airseeker`, `#
B.4 Progress against approved Support / PFI Cost^1^`, `## B.4.1 Cost
variation against approved Support / PFI Cost B.4.1.1 Airseeker Sustainment
and Follow on Development`, `### C.3.3.1 Airseeker`, `## D.3.1 Airseeker`,
`## D.4.1 Airseeker Sustainment and Follow on Development`, `### B.3.1.5
Astute Boat 7`, `### B.4.1.1 Initial Astute Support Solution`, `### B.4.1.2
Astute Class Training Service Boats 1-3`, `### B.4.1.3 Astute Class Training
Service Boat 4`, `### C.5.2.3 Astute Class Training Service Boat 4`, `###
C.5.3.2 Astute Class Training Service Boats 1-3`, `### C.5.3.3 Astute Class
Training Service Boat 4`, `## D.3.3 Astute Boat 5`, `### C.3.3.1 Beyond
Visual Range Air-to-Air Missile (Original In-Service Date)`, `### C.3.3.2
Beyond Visual Range Air-to-Air Missile (In-Service Date 1)`, `### C.3.3.3
Beyond Visual Range Air-to-Air Missile (In-Service Date 2)`, `### B.4.1.1
Through Life Chinook Support`, `### B.4.1.2 New Buy Support`, `### C.3.3.1
Chinook New Buy`, `### C.3.3.2 Julius`, `## D.3.1 Chinook New Buy`, `## D.3.2
Julius`, `## D.4.1 Chinook`, `# B.4 Progress against approved Support / PFI
Cost -N/A`, `## C.3.2 Progress against approved Dates - N/A`, `## C.5.
Support / PFI Contract - N/A`, `## D.3.1 Lightning II`, `## B.3.2 Operational
Impact of cost variations of Demonstration and Manufacture Phase - N/A`, `##
B.4.1 Cost variation against approved Support / PFI Cost - N/A`, `## B.4.2
Operational Impact on Support / PFI Cost - N/A`, `## C.4. Full Operating
Capability - N/A`, `# C.5.3`, `## C.5.4 Other costs / savings resulting from
Support Cost variation -`, `## C.5.5 Operational Impact of Support / PFI
Support Contract variation -`, `## D.4.1 Training Service`, `### D.4.1.3
Operational Impact of variation - N/A`, `# A.6 Associated Projects - N/A`,
`### B.3.1.1 Military Afloat Reach and Sustainability Tanker`, `# B.4
Progress against approved Support / PFI Cost - N/A`, `## C.3.4 Other costs /
savings resulting from timescale variation - N/A`, `## C.3.5 Operational
Impact of In-Service Date/Initial Operating Capability variation - N/A`, `##
D.3.1 Military Afloat Reach and Sustainability Tanker`, `### D.3.1.2 Key
Performance Measures Variation - N/A`, `### D.3.1.3 Operational Impact of
variation - N/A`, `# D.4 Support Contract - N/A`, `### B.3.1.1 Queen
Elizabeth Class Aircraft Carrier`, `### C.3.3.1 Queen Elizabeth Class
Aircraft Carrier`, `## D.3.1 Queen Elizabeth Class Aircraft Carrier`, `##
B.3.1 Cost variation against approved cost of the Demonstration and
Manufacture Phase - N/A`, `## D.2.2 Defence Line of Development variation -
N/A`, `# A.6 Associated Projects - N/A A.7 Procurement Strategy`, `###
B.3.1.1 Warrior Capability Sustainment Programme`, `### C.5.3.1 End of
Contract Date Variation - N/A`, `### B.3.1.1 Astute Boats 1 -3`, `### B.4.1.2
Astute Class Support`, `### B.4.1.3 Astute Class Training Service Boats 1 -
3`, `### B.4.1.4 Astute Class Training Service Boat 4`, `### C.3.3.1 Astute
Boats 1 -3`, `### C.3.3.3 Astute Boat 5 - N/A`, `### C.3.3.4 Astute Boat 6 -
N/A`, `### C.3.3.5 Astute Boat 7 - N/A`, `### C.5.2.2 Initial Astute Support
Solution - N/A`, `### C.5.2.3 Astute Class Support - N/A`, `### C.5.2.4
Astute Class Training Service Boats 1 - 3`, `### C.5.2.5 Astute Class
Training Service Boat 4`, `### C.5.3.2 Initial Astute Support Solution`, `###
C.5.3.3 Astute Class Support - N/A C.5.3.4 Astute Class Training Service
Boats 1 - 3`, `### C.5.3.5 Astute Class Training Service Boat 4`, `## D.3.1
Astute Boats 1 -3`, `## D.3.4 Astute Boat 6`, `### D.3.4.2 Key Performance
Measures variation - N/A`, `### D.3.4.3 Operational Impact of variation -
N/A`, `## D.3.5 Astute Boat 7`, `### D.3.5.2 Key Performance Measures
variation - N/A`, `### D.3.5.3 Operational Impact of variation - N/A`, `###
B.3.1.1 Fire Shadow & Brimstone 2`, `### B.3.1.2 Sea Ceptor Demonstration`,
`### C.3.3.1 Fire Shadow`, `### C.3.3.2 Brimstone 2`, `### C.3.3.3 Sea Ceptor
Demonstration`, `### D.2.1.2 Defence Line of Development variation - N/A`,
`## D.2.2 Brimstone 2`, `# D.2.2.2`, `# D.2.3`, `## D.3.1 Fire Shadow`, `##
D.3.2 Brimstone 2`, `### D.3.2.3 Operational Impact of variation - N/A`, `##
D.3.3 Sea Ceptor Demonstration`, `### D.3.3.2 Key Performance Measures
variation - N/A`, `### D.3.3.3 Operational Impact of variation - N/A`, `###
B.3.1.1 Core Production Capability`, `# C.2 Actual Boundaries for Full
Operating Capability`, `# C.3`, `# C.3.1`, `### C.3.3.1 Core Production
Capability`, `## C.3.5 Operational Impact of Full Operating Capability
variation`, `## C.4. Full Operating Capability - See Above`, `## D.3.1 Core
Production Capability`, `# B.3 Cost of the Demonstration and Manufacture
Phase - N/A`, `### C.5.2.1 Go-Live Date Variation - N/A`, `## A.3. Project
History`, `## A.4. In-Year Progress`, `## A.5. Capability Risks`, `## A.6.
Associated Projects – N/A`, `## A.7. Procurement Strategy`, `## B.2. Cost
Boundaries for Demonstration and Manufacture Phase / PFI`, `# B.4 Progress
against approved Support / Training / PFI Cost`, `## B.4.1 Cost Variation
against approved Support / Training / PFI Cost`, `### B.4.1.1 Training
Service – N/A`, `### B.4.1.2 Increment A – N/A`, `## B.4.2 Operational Impact
of Support / Training / PFI Cost Variations –`, `# C.4 Full Operating
Capability – N/A`, `# C.5 Support / Training / PFI Contract`, `## C.5.1 Scope
of Support / Training / PFI Contract`, `## C.5.2 Progress against approved
Support / Training / PFI Contract Go-Live Date`, `### C.5.2.1 Go-Live Date
Variation – N/A`, `## C.5.3 Progress against approved End of Support /
Training / PFI Contract Date`, `### C.5.3.1 End of Contract Date Variation –
N/A`, `## C.5.4 Other costs resulting from Support Cost variation – N/A`, `##
C.5.5 Operational Impact of Support / Training / PFI Support Contract
variation`, `# D.2 Performance against Defence Lines of Development (DLOD)`,
`# D.3 Performance against Key Performance Measures (KPM)`, `### D.3.1.1
Performance against Key Performance Measures (KPM)`, `### D.3.1.2 Key
Performance Measures Variation – N/A`, `### D.3.1.3 Operational Impact of
variation – N/A`, `## D.4.1 Project/Increment`, `### D.4.1.1 Performance
against Key Performance Measures (KPM)`, `## A.6. Associated Projects`, `#
B.4 Progress against approved Support / Training / PFI Cost – N/A`, `# C.2
Planned / Actual Boundaries for In Service Date or Initial Operating
Capability[^1]`, `## C.3.3 Timescale variation – N/A`, `## C.3.4 Other costs
resulting from Timescale variation – N/A`, `## C.3.5 Operational Impact of
In-Service Date/Initial Operating Capability variation – N/A`, `# C.4 Full
Operating Capability`, `# C.5 Support / Training / PFI Contract – N/A`, `##
C.5.1 Scope of Support / Training / PFI Contract – N/A`, `## C.5.2 Progress
against approved Support / Training / PFI Contract Go-Live Date – N/A`, `##
C.5.3 Progress against approved End of Support / Training / PFI Contract Date
– N/A`, `## C.5.5 Operational Impact of Support / Training / PFI Support
Contract variation – N/A`, `## D.3.1 Lightning II Key User Requirements as
laid down in the LII User Requirement Document v7.0`, `# D.4 Support Contract
– N/A`, `## B.4.1 Cost Variation against approved Support / Training / PFI
Cost –`, `## C.5.4 Other costs resulting from Support Cost variation`, `##
D.3.1 Queen Elizabeth Class Aircraft Carriers`, `# C.3 In-Service
Date/Initial Operating Capability – N/A`, `## C.3.2 Progress against approved
Dates – N/A`, `## D.2.1 Defence Lines of Development Variation – N/A`, `##
D.3.1 Recce Block 1 Demonstration`, `### B.3.1.3 Meteor Integration`, `###
B.3.1.4 Storm Shadow Integration N/A`, `### B.4.1.1 Typhoon`, `## B.4.2
Operational Impact of Support / Training / PFI Cost Variations`, `### C.3.3.3
Meteor Integration`, `### C.3.3.4 Storm Shadow Integration`, `## C.5.3
Progress against approved End of Support / Training / PFI Contract Date–
N/A`, `## C.5.4 Other costs resulting from Support Cost variation– N/A`, `##
C.5.5 Operational Impact of Support / Training / PFI Support Contract
variation– N/A`, `### D.3.2.1 Performance against Key Performance Measures
(KPM)`, `### D.3.2.2 Key Performance Measures Variation- N/A`, `### D.3.2.3
Operational Impact of variation – N/A`, `## D.3.3 Meteor Integration`, `###
D.3.3.1 Performance against Key Performance Measures (KPM)`, `### D.3.3.2 Key
Performance Measures Variation – N/A`, `### D.3.3.3 Operational Impact of
variation – N/A`, `## D.3.4 Storm Shadow Integration`, `### D.3.4.1
Performance against Key Performance Measures (KPM)`, `### D.3.4.2 Key
Performance Measures Variation – N/A`, `### D.3.4.3 Operational Impact of
variation – N/A`, `### D.4.1.3 Operational Impact of variation – N/A`, `##
C.3.2a Progress against Budgeted for Date at approval`, `## C.3.2b Progress
against Approval Date`, `### C.3.3.1 Warrior Capability Sustainment
Programme`, `### B.3.1.3 Astute Boat 4`, `### B.3.1.4 Astute Boat 5`, `###
B.3.1.5 Astute Boat 6`, `# C.3.3.3`, `### C.3.3.4 Astute Boat 6 – N/A`, `###
C.3.3.5 Astute Boat 7 – N/A`, `### C.5.3.2 Initial Astute Support Solution –
N/A`, `### C.5.3.3 Astute Support – N/A`, `### C.5.3.4 Astute Class Training
Service Boats 1-3`, `### C.5.3.5 Astute Class Training Service Boat 4 – N/A`,
`### D.3.5.1 Performance against Key Performance Measures (KPM)`, `###
D.3.5.2 Key Performance Measures Variation – N/A`, `### D.3.5.3 Operational
Impact of variation – N/A`, `### B.3.1.2 Sea Ceptor Demonstration &
Manufacture`, `### B.3.1.3 Future Anti-Surface Guided Weapon (Heavy)`, `###
B.3.1.4 Future Anti-Surface Guided Weapon (Light)`, `### B.3.1.3 Brimstone
Unified Support Contract – N/A`, `### C.3.3.1 Fire Shadow – N/A`, `###
C.3.3.3 Sea Ceptor Demonstration & Manufacture – N/A`, `### C.3.3.4 Future
Anti-Surface Guided Weapon (Heavy) – N/A`, `### C.3.3.5 Future Anti-Surface
Guided Weapon (Light) – N/A`, `## D.2.1 Fire Shadow – N/A`, `### D.2.1.2
Defence Lines of Development Variation`, `### D.2.2.1 Brimstone 2`, `###
D.2.2.2 Defence Lines of Development Variation`, `### D.2.3.1 Sea Ceptor
D&M`, `### D.2.3.2 Defence Lines of Development Variation – N/A`, `###
D.2.3.1 Future Anti-Surface Guided Weapon (Heavy)`, `### D.2.4.1 Future
Anti-Surface Guided Weapon (Light)`, `### D.2.4.2 Defence Lines of
Development Variation – N/A`, `## D.3.1 Fire Shadow – N/A`, `## D.3.3 Sea
Ceptor D&M`, `## D.3.4 Future Anti-Surface Guided Weapon (Heavy)`, `## D.3.5
Future Anti-Surface Guided Weapon (Light)`, `# D.4 Support Contract –
Brimstone Weapon System Support - USE`, `### D.4.1.2 Key Performance Measures
Variation – N/A`, `## C.3.1 Definition</td>`, `# C.4 Full Operating
Capability – see above`, `## A.6. Associated Projects - N/A`, `# B.4 Progress
against approved Support / Training / PFI Cost</td>`, `### B.4.1.1 Training
Service`, `### B.4.1.2 In Service Support`, `# D.4 Support and Training
Contract`, `## D.4.1 Training`, `### D.4.2.2 Key Performance Measures
Variation – N/A`, `## D.4.2 In-Service Support`, `### D.4.2.1 Performance
against Key Performance Measures (KPM)`, `### D.4.2.3 Operational Impact of
variation – N/A`, `# A.4 In-Year Progress`, `# A.6 Associated Projects –
N/A`, `## B.2. Cost Boundaries for Through Life Contract`, `## B.3. Cost of
the Demonstration and Manufacture and In-Service Phase`, `# D.1 Sentinel
Score as at 31/03/2015`, `## D.3.1 Marshall`, `### B.3.1.1 Military Afloat
Reach and Sustainability Tanker (In-Year)`, `### B.3.1.1.1 Military Afloat
Reach and Sustainability Tanker (Historic)`, `### B.4.1. Cost variation
against approved Support / PFI Cost (In Year) –`, `### C.3.3.1 Military
Afloat Reach and Sustainability Tanker – N/A`, `### B.3.1.1 Queen Elizabeth
Class Aircraft Carrier (In-Year) – N/A`, `### B.3.1.1.1 Queen Elizabeth Class
Aircraft Carrier (Historic)`, `### C.3.3.1 Queen Elizabeth Class Aircraft
Carriers (In-Year)`, `### C.3.3.2 Core Production Capability (Historic)`, `##
B.4.1 Cost variation against approved Support / PFI Cost (In Year) –`, `###
C.3.3.1 Recce Block 1 & 2 (Demonstration) STR`, `## D.3.2 Project/Increment –
N/A`, `### D.3.2.1 Performance against Key Performance Measures (KPM) – N/A`,
`### D.3.2.2 Key Performance Measures Variation – N/A`, `## A.3. In-Year
Progress`, `## B.3.1 Demonstration Phase – N/A`, `## B.3.2 – N/A`, `# D.1
Technology Readiness Level`, `# D.2 Performance against Defence Lines of
Development (DLOD) – N/A`, `# D.3 Performance against Key Performance
Measures (KPM) – N/A`, `### B.3.1.1 Typhoon (In-Year)`, `### B.3.1.2 Typhoon
(Historic)`, `### B.3.1.3 Typhoon Future Capability Programme (In-Year)`,
`### B.3.1.4 Typhoon Future Capability Programme (Historic)`, `### B.3.1.5
Meteor Integration (In-Year)`, `### B.3.1.6 Meteor Integration (Historic)`,
`### B.3.1.7 Storm Shadow Integration (In-Year)`, `### B.3.1.8 Brimstone 2
Integration – N/A`, `## B.3.2 Operational Impact of Cost Variations of
Demonstration & Manufacture Phase – N/A B.4 Progress against approved Support
/ Training / PFI Cost`, `### B.4.1.1 Typhoon (In-Year)`, `### B.4.1.2 Typhoon
(Historic)`, `### C.3.3.1 Typhoon (In-Year) – N/A`, `### C.3.3.2 Typhoon
(Historic)`, `### C.3.3.3 Typhoon Future Capability Programme (In-Year) –
N/A`, `### C.3.3.4 Typhoon Future Capability Programme (Historic)`, `###
C.3.3.5 Meteor Integration (In-Year) – N/A`, `### C.3.3.6 Storm Shadow
Integration (In-Year) – N/A`, `### C.3.3.7 Brimstone 2 Integration (In-Year)
– N/A`, `## D.3.5 Brimstone 2 Integration`, `### B.4.1.1 Future Strategic
Tanker Aircraft (In-Year)`, `### B.4.1.2 Future Strategic Tanker Aircraft
(Historic)`, `### B.3.1.1 Warrior Capability Sustainment Programme
(In-Year)`, `### B.3.1.2 Warrior Capability Sustainment Programme
(Historic)`, `### B.4.1.1 Battle Group Thermal Imaging (In-Year) – N/A`, `###
B.4.1.1.1 Battle Group Thermal Imaging (historic)`, `### B.4.1.2 Diesel
Engines and Transmissions (In-Year) – N/A`, `### B.4.1.2.1 Diesel Engines and
Transmissions (Historic)`, `### B.4.1.3 Diesel Engines and Transmissions
(new)`, `### C.3.3.1 Warrior Capability Sustainment Programme (In-Year) –
N/A`, `### C.3.3.2 Warrior Capability Sustainment Programme (Historic)`, `##
A.4. In-Year Progress Approvals`, `### B.3.1.1 Astute Boats 1 -3 (In-Year)`,
`### B.3.1.2 Astute Boats 1 -3 (Historic)`, `### B.3.1.3 Astute Boat 4
(In-Year)`, `### B.3.1.4 Astute Boat 4 (Historic)`, `### B.3.1.5 Astute Boat
5 (In-Year)`, `### B.3.1.6 Astute Boat 5 (Historic)`, `### B.3.1.7 Astute
Boat 6 (In-Year)`, `### B.3.1.8 Astute Boat 6 (Historic)`, `### B.3.1.9
Astute Boat 7 (In-Year)`, `### B.3.1.10 Astute Boat 7 (Historic)`, `###
B.4.1.1 Initial Astute Support Solution (In–Year) – N/A`, `### B.4.1.2
Initial Astute Support Solution (Historic)`, `### B.4.1.3 Astute Class
Support (In-Year)`, `### B.4.1.4 Astute Class Support (Historic)`, `###
B.4.1.5 Astute Class Training Service Boats 1-3 (In-Year)`, `### B.4.1.6
Astute Class Training Service Boats 1-3 (Historic)`, `### B.4.1.7 Astute
Class Training Service Boat 4 (In-Year)`, `### B.4.1.8 Astute Class Training
Service Boat 4 (Historic)`, `### C.3.3.1 Astute Boats 1-3 (In-Year) – N/A`,
`### C.3.3.2 Astute Boats 1-3 (Historic)`, `### C.3.3.3 Astute Boat 4
(In-Year) – N/A`, `### C.3.3.4 Astute Boat 4 (Historic)`, `### C.3.3.5 Astute
Boat 5 – N/A`, `### C.3.3.6 Astute Boat 6 – N/A`, `### C.3.3.7 Astute Boat 7
– N/A`, `### C.5.2.4 Astute Class Training Service Boats 1 – 3 (In-Year) –
N/A`, `### C.5.2.5 Astute Class Training Service Boats 1 – 3 (Historic)`,
`### C.5.2.6 Astute Class Training Service Boat 4 (In-Year) – N/A`, `###
C.5.2.7 Astute Class Training Service Boat 4 (Historic)`, `### C.5.3.3 Astute
Support`, `### C.5.3.4 Astute Class Training Service Boats 1-3 (In-Year) –
N/A`, `### C.5.3.4 Astute Class Training Service Boats 1-3 (Historic)`, `###
B.3.1.1 Fire Shadow & Brimstone 2 (In-Year)`, `### B.3.1.1.1 Fire Shadow &
Brimstone 2 (Historic)`, `### B.3.1.2 Sea Ceptor Demonstration & Manufacture
(In-Year) – N/A`, `### B.3.1.2.1 Sea Ceptor Demonstration & Manufacture
(Historic)`, `### B.3.1.3 Future Anti-Surface Guided Weapon (Heavy)
\\[In-Year\\]`, `### B.3.1.3.1 Future Anti-Surface Guided Weapon (Heavy)
\\[Historic\\]`, `### B.3.1.4 Future Anti-Surface Guided Weapon (Light)
\\[In-Year\\]`, `### B.3.1.4.1 Future Anti-Surface Guided Weapon (Light)
\\[Historic\\]`, `### B.3.1.5 Land Ceptor GBAD Phase 1 \\[In-Year\\]`, `###
C.3.3.2 Brimstone 2 (In-Year)`, `### C.3.3.3 Brimstone 2 (Historic)`, `###
D.2.5.1 Land Ceptor (GBAD-Phase 1)`, `## D.3.6 Land Ceptor (GBAD-Phase 1)`,
`### D.3.6.2 Key Performance Measures Variation – N/A`, `# D.4 Support
Contract – USE`, `## D.4.1 Brimstone Weapon System Support - USE`, `## D.4.2
ASRAAM Weapon System Support - USE`, `### B.3.1.1 Core Production Capability
(In-Year)`, `### B.3.1.1.1 Core Production Capability (Historic)`, `# B.4
Progress against approved Support / PFI Cost – N/A`, `### C.3.3.1 Core
Production Capability (In-Year)`, `# D.3 Performance against Key Performance
Measures (KPM) - N/A`, `## D.3.1 Core Production Capability – N/A`, `###
B.3.1.1 System Development & Demonstration (In-Year)`, `### B.3.1.2 System
Development & Demonstration (Historic)`, `### B.3.1.3 Production, Sustainment
& Follow on Development (In-Year)`, `### B.3.1.4 Production, Sustainment &
Follow on Development (Historic)`, `# C.1 Length of the Assessment
Phase[^1]`, `## D.3.1 Lightning II Key User Requirements as laid down in the
LII User Requirement`)`.